The four works that aim to improve mobility in the city of Cancun continue at a rapid pace and the fact is that recently, the governor of the state, Mara Lezama, has announced that the progress has been progressive and many of them could be completed by the end of this year. and beginnings of the next.

The Luis Donaldo Colosio boulevard was the first work to begin in the city and to date an advance of 50 percent has been registered, while the road distributor of the Cancun International Airport already has 40 percent, so they would be the first to conclude during October of this year.

On the other hand, the remodeling of Chac Mool avenue is about to reach 5 percent progress and due to the dynamism represented by its workers, it could be ready for the month of December.

While the largest federal project in the city, the Laguna Nichupté Bridge already has a 14 percent progress and assured that the work has not stopped since it began in July 2022.

According to the president, the work on the Nichupté Lagoon Bridge is estimated to be completed at the beginning of next year and would begin to operate during the month of March 2024.

It should be remembered that these four macro works add up to a historic investment of 8 thousand 806 million pesos that will benefit the inhabitants of the municipalities of Benito Juárez, Isla Mujeres, Puerto Morelos and Solidaridad; as well as the more than 20 million tourists that the area receives each year, generating 10,000 direct jobs and 41,000 indirect jobs, all in favor of thousands of families from Quintana Roo.