The broadcast in SVT1 was also down for a couple of minutes but was back at 6.44.

At 06.40 on Wednesday morning, the subway came to a complete stop in the inner city. The green line could start running again after five or six minutes, but only at 07.30 SL announced on its website that traffic on all lines was up and running again.

– We have had disruptions on the subway and local lines due to a power outage at Svenska Kraftnät, says Helene Jakobsson, press communicator at the Transport Administration in the Stockholm region.

Departures have been canceled and travelers should prepare for delays. The traffic administration urges you to keep an eye on signage and in SL’s app.

Svenska Kraftnät is investigating the cause

Svenska Kraftnät states that they are investigating the cause of the power outage.

– We have ascertained what happened and are in the process of reviewing what caused the power outage. We do not know whether it is our facilities or the regional ones that have failed at the moment. At the moment we have nothing more to share, says Joel Nylin, press communicator at Svenska Kraftnät.

Forsmark 1 and 2 are down

Right now, production is also down for the Forsmark 1 and 2 nuclear power reactors.

– It is true that Forsmark 1 and 2 have left the network, says Josef Nylén, press manager at Forsmark.

According to Josef Nylén, it is the disturbance in Svenska Kraftnät that forced the reactors to go down.

– Something has happened on the main network. We lost power for a short period. Our backup power systems have been working as they should, but since we lost the input, we cannot operate the reactors and produce electricity, says Josef Nylén.

Reactor 3 is still producing and has not been disrupted. Now some routine tests and initial checks must be done before reactors 1 and 2 can produce electricity again.

– Exactly when we can go up again is unclear, but we are working hard, says Josef Nylén.

What does this mean for the electricity supply in Sweden and the electricity price?

– There are more electricity producers, but Forsmark 1 and 2 are a significant part of Sweden’s electricity production. We are working to be back up as quickly as possible.

No major delays for SJ trains

SJ says that their train services have not had any major disruptions as a result of the power outage, although individual trains may have been affected for a shorter period of time.